John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd

(1996) 8 VR 681Supreme Court of VictoriaGlobal claims and causation

What was the issue?

The dispute involved complex design and construction allegations and a claim that multiple events contributed to overall cost and delay. The pleading raised the familiar problem of how a claimant connects numerous alleged causes to an aggregated loss.

What is the practical principle?

Where separating every cause and consequence is genuinely impossible or impractical, a claimant may seek to demonstrate the probable existence of the required connection. However, the claim remains exposed if unrelated causes, claimant-responsible events or unproven costs are rolled into the total.

Why Daily Records matter

Detailed daily records make it easier to separate events, resources and costs before they become an undifferentiated total. They can help commercial teams identify when an event began, which workfront was affected, which resources were used and how long the impact continued.

Practical lessons for contractors

Build the connection while the work is happening

MyCommercialManager structures Daily Records so the factual record, evidence, resource usage, value and acknowledgement history remain connected and exportable.