White Constructions Pty Ltd v PBS Holdings Pty Ltd

[2019] NSWSC 1166Supreme Court of New South Wales6 September 2019

What happened?

A developer alleged that delays in sewer design and approval delayed completion of a residential subdivision and caused loss. Both sides relied on programming experts using different delay-analysis methods.

What did the Court decide?

The proceedings were dismissed. The Court was not satisfied that breach or the claimed delay and damages had been established. The judgment emphasised close attention to the factual evidence rather than treating a chosen delay methodology as determinative.

Why the records mattered

The evidence included a site diary, but the relevant entries did not adequately identify which activities were affected or demonstrate the particular consequences of the alleged delay. General evidence was insufficient to establish the required causal findings.

Practical lessons for contractors

How MyCommercialManager supports the record

Daily Records keep work performed, labour, plant, materials, site notes, timestamped evidence and the acknowledgement trail connected under one reference.

Start Free

Source and disclaimer

This note is general educational information, not legal advice. It is a practical summary rather than an official report of the decision. Read the judgment and obtain professional advice for a particular contract or dispute.

Read the published judgment text →